Plant layout planning and funding application for an energy plant at a timber merchant
Planning and funding support from a single source
Project at a glance
| Project type: | Engineering |
|---|---|
| Client: | Timber merchant |
| Location: | Germany |
| Fuel: | Residues from the company’s own timber trade |
| Our scope: | Plant layout planning and funding support |
| Implemented by: | ClinX Energy Systems GmbH, pyropower group |

From layout plan to funding application
Starting point
A timber merchant already has its fuel in the yard. What remained open was where and how a plant could sensibly be set up on site and how the project could be funded.
Implementation
ClinX Energy Systems first planned the layout of the plant: space requirements, connection to the heat consumers and the routes for the fuel from storage to feeding. The next step was the assignment to support the funding procedure.
Result
This resulted in a technical layout plan and a supported funding application, the two most important foundations for the decision to go ahead.
Thinking planning and funding together
The layout plan and the funding application are closely linked: the application needs reliable technical data, and the planning has to take the conditions of the funding programme into account. Handled from a single source, both steps mesh together.
[ Knowledge ]
Funding for energy plants: application first, then the order
- Project start: in many programmes, the conclusion of a supply or service contract
- Not a project start: planning, consulting and permitting procedures
- Consequence: placing an order before applying usually means losing the entitlement to funding
Most funding programmes for companies, for example from BAFA or KfW, require the application to be submitted before the project starts. The start is usually considered to be the conclusion of a supply or service contract attributable to execution, for example ordering the plant.
Planning and consulting services, on the other hand, usually do not count as the start of the project. A layout plan, an economic assessment or a permitting procedure can therefore come before the application and even provide the information the application needs. Some programmes also allow contracts that are subject to the funding approval.
Because programmes, funding rates and conditions change regularly, it is worth checking the current guideline before every step. Anyone using residues from their own business should also clarify early on which fuel documentation is required.
From the blogForest residues as feedstock: quality, availability and rules for pyrolysisRead more ›
[ Technology ]
Engineering and concepts
From the pre-project phase through concept and economic viability to detailed engineering: we design energy plants for residues, process heat and heating networks.
[ References ]
Latest projects
Biochar production at an industrial site in Mecklenburg-Western Pomerania
Three Pyro-ClinX 150 plants produce power, heat and biochar from industrial wood residues at an industrial site in Mecklenburg-Western Pomerania.
PyroPark Forst
PyroPark Forst is being developed in Lusatia as an integrated energy site that converts woody residues into electricity, usable heat, biochar and certified carbon removal.
ClinX Heat Power Generation from a Carbonization Plant in Darmstadt
ClinX Heat uses high-temperature energy from an existing carbonization plant to generate additional electricity on site.